The year 2022 was a year which saw a boom in commodity markets post-Covid. The need for new grinding mills for projects being developed worldwide was high, with foundries and fabrication workshops filled with new orders. Lead times for components were being increased dramatically based on full order books.
Early 2022, NCPI was approached by Hummingbird Resources plc to supply an 18’Ø x 31, 4.5 MW SAG Mill for their Kouroussa Gold Mine (KGM) in Guinea. NCPI discussed the needs and expectations of the customer to understand their specific project requirements clearly.
Delivery ex-manufacturing works had to be achieved within a timeframe to meet the installation schedule. The project also had to be within the budget and quality requirements.
Based on well-developed relationships with key suppliers, NCPI planned the manufacture of the grinding mill components to meet the delivery schedule.
NCPI was commissioned to manage the delivery of the mill components to Guinea in conjunction with the Hummingbird Resources plc team. This involved the packing and delivery of 500 tonnes of equipment from various manufacturing points worldwide.
Further, NCPI had assisted Hummingbird Resources plc with a team of instrumentation, mechanical, and automation technicians to ensure that the SAG mill commissioning was completed efficiently and successfully.
Some graphic details below highlighting the SAG Mill transportation and installation.
Abnormal road freight of the 50-tonne mill shell sections in South Africa